http://training.ey.hu/images/upload/file/usgaap_text.pdf
1. Accounting issue
The accounting issue is one
of revenue recognition
1.1
Authoritative
Pronouncement
ARB 45 – long term construction type
contracts
SOP 81-1 – long term construction type
contracts
1.2
Illustration
A company enters into a contract to
construct a football stadium. The contract iw worth $200 million dollars and
will last for three years. The expected costs have been estimated as follows:
Year 1 $80 million
Year 2 $60 million
Year 3 $40 million
Overall estimated profit $20 million
The question is whether to recognise any
profit and revenue only when the contract is completed and the stadium is
delivered? This would be prudent but would not reflect the earnings of the
business in the income statement.
Alternatively the profit could be
allocated, together with a proportion of revenue, to each of the three years of
the project. This could be match income-to-income earning activities but would
it be prudent?
1.3
Definition
There is no formal definition of a
qualifying long-term contract within US GAAP but this treatment may apply to
contracts where
(a)
Gross profit is
taken on a % complete basis
(b)
Inventories and
receivables are material and the contract duration is expected to be more than
12 months
(c)
Ownership effectively
passes to the customer throughout the course of the contract
2. Completed contract method
For those contracts when the
future costs cannot be reliably estimated or if the contract is anticipated to
be loss making
2.1
Accounting treatment
Direct costs
and overheads are booked to a construction-in-progress account (asset)
Billings are
charged to a billings in advance account (liability)
Individual
contract balances should be netted off at the balance sheet date
At completion
the total costs and income and transferred to net income
2.2 expected losses
These should be recognize in
full over the duration of the contract. The loss should be recorded in net
income and deducted from the construction-in-progress account.
3. Percentage of completion method
This method should be used for those contracts which are
profitable and for which
amounts of future costs can be reliably estimated.
3.1 Accounting treatment
In addition to the recognition of costs as for completed
contracts method, each year an
amount of gross profit should be added to the
construction asset.
This profit may be calculated either as a percentage of
costs incurred to date, by the
value of certified work compared to the total contract
value or some other reasonable
basis.
3.2 Losses on contracts
The percentage complete method is not available for loss
making contracts. In addition
any losses on contracts should be recognized at the point
of recognition. You will also
need to cancel any profits previously recognized.
3.3 Illustration
Able Inc has entered into a fixed price contract worth
$10m. The estimated costs of the
contract are as follows:
Year 1 2
3
Costs 2,000,000 5,000,000 1,000,000
The contract qualifies to be accounted for on a
percentage of completion basis as
follows:
Year 1
Revenue recognized
based on cost incurred
$
$ 2 , 000 , 000
$10m x
2,500,000
$ 8 , 000 , 000
Costs incurred
(2,000,000)
Gross profit
500,000
Construction in
progress asset
$(2,000,000 +
500,000) 2,500,000
In year 2 costs
are as estimated
Revenue earned to
date:
$7 ,
000 , 000 x $10,000,000 = 8,750,000
$ 8 , 000 , 000
Less recognised
in year 1 (2,500,000)
Year 2 revenue
6,250,000
Cost incurred
5,000,000
Gross profit
1,250,000
Construction in progress
asset 8,750,000
$(2,000,000 +
500,000 + 5,000,000 + 1,250,000)
The above presumes that no invoices are raised on
account of work completed.
In year 3 now suppose that actual costs come to
$2,000,000 with a further $2,000,000
required in year 4 when the contract will be
completed.
In this situation the contract is now loss making.
Revenue (as before) 10,000,000
Cost year 1 2000,000
2 5000,000
3 2000,000
Estimated
Year 4 2000,000 (11,000,000)
Anticipate loss recognized immediately (1000,000)
The profit taken to date must also be cancelled
Profit taken
Year 1 500,000
2 1250,000
(1750,000)
Gross loss recognized in year 3 (2750,000)
The balance sheet asset will then be restated
Balance brought forward 8750,000
Add costs incurred 2000,000
10,750,000
Less loss provision (2750,000)
Construction in progress asset 8,000,000
Year 4 -- contract completed
Construction in progress asset b/fwd 8000,000
Add costs incurred 2000,000
10,000,000
Less invoiced contract value (10,000,000)
Closing balance -----
No comments:
Post a Comment